PUBLIC INVOLVEMENT IN STATEWIDE PLANNING

The following is an exerpt from the Final Rule on Statewide Planning and Metropolitan Planning

Federal Highway Administration and Federal Transit Administration
23 CFR Part 450 and 49 CFR Part 613
Issued on: October 22, 1993


§ 450.212 Public involvement.

(a) Public involvement processes shall be proactive and provide complete information, timely public notice, full public access to key decisions, and opportunities for early and continuing involvement. The processes shall provide for:

(1) Early and continuing public involvement opportunities throughout the transportation planning and programming process;
(2) Timely information about transportation issues and processes to citizens, affected public agencies, representatives of transportation agency employees, private providers of transportation, other interested parties and segments of the community affected by transportation plans, programs and projects;
(3) Reasonable public access to technical and policy information used in the development of the plan and STIP;
(4) Adequate public notice of public involvement activities and time for public review and comment at key decision points, including but not limited to action on the plan and STIP;
(5) A process for demonstrating explicit consideration and response to public input during the planning and program development process;
(6) A process for seeking out and considering the needs of those traditionally underserved by existing transportation systems, such as low-income and minority households which may face challenges accessing employment and other amenities;
(7) Periodic review of the effectiveness of the public involvement process to ensure that the process provides full and open access to all and revision of the process as necessary.

(b) Public involvement activities carried out in a metropolitan area in response to metropolitan planning requirements in § 450.322(c) or § 450.324(c) may by agreement of the State and the MPO satisfy the requirements of this section.

(c) During initial development and major revisions of the statewide transportation plan required under § 450.214, the State shall provide citizens, affected public agencies and jurisdictions, employee representatives of transportation and other affected agencies, private and public providers of transportation, and other interested parties a reasonable opportunity to comment on the proposed plan. The proposed plan shall be published, with reasonable notification of its availability, or otherwise made readily available for public review and comment. Likewise, the official statewide transportation plan (see §450.214(d)) shall be published, with reasonable notification of its availability, or otherwise made readily available for public information.

(d) During development and major revision of the statewide transportation improvement program required under § 450.216, the Governor shall provide citizens, affected public agencies and jurisdictions, employee representatives of transportation or other affected agencies, private providers of transportation, and other interested parties, a reasonable opportunity for review and comment on the proposed program. The proposed program shall be published, with reasonable notification of its availability, or otherwise made readily available for public review and comment. The approved program (see §450.220(c)) if it differs significantly from the proposed program, shall be published, with reasonable notification of its availability, or otherwise made readily available for public information.

(e) The time provided for public review and comment for minor revisions to the statewide transportation plan or statewide transportation improvement program will be determined by the State and local officials based on the complexity of the revisions.

(f) The State shall, as appropriate, provide for public comment on existing and proposed procedures for public involvement throughout the statewide transportation planning and programming process. As a minimum, the State shall publish procedures and allow 45 days for public review and written comment before the procedures and any major revisions to existing procedures are adopted.

(g) The public involvement processes will be considered by the FHWA and the FTA as they make the planning finding required in § 450.220(b) to assure that full and open access is provided to the decision making process.